Qued Athmania Water Treatment Plant (Phase 1)

Project Details

Location
Algeria
Year
Mar 2005 – Dec 2006
Consultant
Degremont
Scope Of Work
Design, Material Supply, Civil & Structural Works, Pipeline Construction
The water treatment plant contract was awarded to the ENKA & Degremont (France) Consortium. The scope of construction included:
  • Detailed design.
  • Material supply.
  • Civil and structural works for the treatment plant.
  • Leakage testing of all structures.
ENKA’s Share of Work:
  • Design, supply, erection, and start-up of the raw water supply pipeline.
The facility was designed with a final operational capacity of 270,000 m³/day of treated water.